IBM Corp.

Central Utility Plant Master Plan
Essex Junction, Vt.

Project cost 
$ n/a
The smart solution 

WM Group's $12 million plan for reusing existing chiller plant capacity saved capital costs against the $42 million plan proposed by other consultants. Proposed expansion of district heating and cooling systems.

Time frame 

1995 to 1997

Practice areas involved 
District cooling systems
District heating systems
Key services provided 
Planning
System optimization
Design
Construction administration
Peer review